Below is a detailed summary of the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building in Armenia.
No. | Procedure | Time to Complete | Associated Costs |
---|---|---|---|
1 | Submit an application to the Electrical Networks of Armenia and await technical conditions Agency: Electric Networks of Armenia (ENA) The application can be submitted online since January 1, 2013 according to the PSRC Resolution N208-N dated June 13, 2012. The website is: www.ena.am. A legal entity has to submit an application accompanied with certificate of state cadaster, tax code, bank account info, certificate of privatization of the land/area (in case of a land lease the agreement of the property owner), a notary certified authorization of the person acting on behalf of the legal entity. Applicant should also submit information on requested capacity, voltage level, connection type (single-phase, three-phase) and connection point(s) as well as request for an alternative power supply. Online application also requires a copy of passport and an e-mail address of the company’s director, private entrepreneur, physical entity or their authorized persons. ENA prepares technical conditions and cost estimates. These conditions apply only to parts of the external connection and do not apply to internal wiring. As a rule, they can contain instructions for installing a new substation; cabling of the high and low voltage. In the preparation of technical specifications, ENA must conform them to the applicant. After development of technical conditions, ENA will prepare the electrical design and cost estimation documents, and obtain all approvals required by number of government agencies. Finally, ENA will submit Connection Contract to the Applicant signed by ENA that provides information on date when connection works will be completed, connection cost and payment procedure. |
52 calendar days | AMD 0 |
* 2 | Await and obtain site inspection from the Electrical Networks of Armenia Agency: Electric Networks of Armenia (ENA) The Electrical Networks of Armenia inspect the site to aid the preparation of technical conditions. It is required that someone from the applicant’s party is present at the site during the inspection. |
1 calendar day | AMD 0 |
3 | Await completion of the external connection works by the Electrical Networks of Armenia Agency: Electric Networks of Armenia (ENA) All connection works including cable laying and installation of a meter are performed by ENA and its subcontractor. Subcontractors also obtain the excavation permit. Connection fees are established according to the PSRC Resolutions N 658-N and N 659-N dated December 21, 2007. The connection fee is excluding VAT. |
125 calendar days | AMD 1,394,166.67 |
4 | Await and obtain inspection of the completed external connection works and internal wiring from the Electrical Networks of Armenia Agency: Electrical Networks of Armenia Electrical Networks of Armenia complete inspection of the works. |
7 calendar days | AMD 0 |
5 | Sign supply contract with the Electrical Networks of Armenia and receive final connection Agency: Electrical Networks of Armenia The electricity will start flowing as soon as the supply contract between ENA and the applicant is concluded. |
3 calendar days | AMD 0 |